Build a stakeholder map from a kickoff. Record interests, influence, decision authority, and a communication plan. Includes a matrix and template.

The Transkribator team5-minute read
SOURCEPROJECT STAKEHOLDERSSponsor:Support:UsersAdministratorFROM WORDS TO RESULTS
Working from a real recordingWorked training exampleTemplate to copy
Project management

Who is missing from the attendee list?

A manager may discuss the rollout even though other employees will use the result every day. The person who grants data access or gives final approval may be absent. Treat the attendee list as a starting point.

Use the map to decide who should discuss a decision, see a prototype, or simply hear about the change. It does not rank people. Influence depends on the question and can change across project phases.

Steps

Build the map in four passes

  1. Name the project outcome

    Describe the change in one sentence and list the affected activities. For example, staff will enter requests in a shared system. Ask who creates, checks, uses, and maintains the data. This reveals stakeholders who missed the kickoff.

  2. Separate interests and authority

    Record what the person wants to gain or preserve and what decisions they can make. An active participant may lack budget authority. Mark claims about authority that come from a colleague as needing confirmation.

  3. Decide how to involve each stakeholder

    For each issue, choose whether to decide jointly, ask for advice, show a draft, or send the result. Avoid inviting everyone to every meeting by default. State what event triggers their involvement.

  4. Verify and maintain the map

    Send stakeholders their relevant roles and agreements. Identify anyone missing. Review the map when the phase, sponsor, or decision owner changes. Different people may run the pilot and approve the full rollout.

Worked example

Launching a single customer inquiry form

This fictional example uses names, conditions, and outcomes solely to explain the method.

Excerpt from a practice recording · 12:40
I approve the form, but the support lead knows which fields are required. Staff will fill it in daily. The administrator grants access to the old data.

That one remark calls for four different conversations. Approving the appearance does not approve the fields, and granting access does not make someone responsible for data quality.

The example matrix shows actions for this situation. On a real project, clarify each stakeholder’s interests and influence first, then choose how to engage them.

Sponsor: approvethe resultSupport: checkthe fieldsUsers: trythe workflowAdministrator:prepare accessA sample engagement plan for this situation
People in the same meeting may need different kinds of involvement. The map connects roles to actions.
StakeholderWhat to clarifyWhen to involve them
SponsorWho approves the final versionBefore approving the form
SupportWhat information is needed to respondWhile designing the fields
UsersWhat is unclear when filling it inDuring a trial run
AdministratorAccess requirements and limitsBefore migrating working data
Ready-to-use template

Stakeholder map and communication plan

Record the specific issue that needs this stakeholder’s involvement alongside their name or role.

Template for your workSelect and copy
Stakeholder / working role:
How the outcome affects them:
Interest or expectation:
Decisions they can make:
What remains unconfirmed:
How to involve them:
Event that triggers involvement:
Who keeps in touch:
Source: meeting, timecode, confirmation:
Next review date:
Result check

Check who needs to join your next call

  • The map includes users of the result even if they missed the kickoff.
  • Decision authority is distinguished from team assumptions.
  • Each stakeholder has a clear question or action.
  • The map has a date and project phase.
StakeholdersWho the work affectsInterestsWhat they needInvolvementDecision or feedbackReviewRoles confirmed
The map is useful when it leads to a concrete communication plan.
Frequently asked questions

A closer look

How does a stakeholder map differ from RACI?

A map shows who is affected and how to engage them. RACI assigns roles for specific tasks. The two documents complement each other.

Do we have to score everyone numerically?

No. For a small team, explain influence, interest, and the involvement needed. Scores without agreed criteria create an impression of precision.